Reports by the Commission

Opinions

Approvals and Other Rulings

  • With the opening of the Golden Ears Bridge, Commission Memorandum 2, dated June 26 2009, notifies TransLink that the Commissioner has no objection to the sale of Albion Ferry assets.
  • Commission Order 09-01, dated April 30 2009, determines that an Airport Special Zone Fare on the Canada Line, to open later in 2009, does not require Commission approval.
  • Commission Order 08-01, dated December 15 2008, approves TransLink’s Customer Satisfaction Survey Process. Here is an Executive Summary.
  • Commission Order 08-02 under section 225 of the SCBCTA Act, dated December 19 2008 conditionally approves TransLink’s Customer Complaints Process. Here is an Executive Summary.